Home » Canyon Raises A$70m to Develop Cameroon Bauxite Project

Canyon Raises A$70m to Develop Cameroon Bauxite Project

by Adedotun Oyeniyi

KEY POINTS


  • Canyon Resources is seeking to raise about A$70-million to fund development and initial operations at its Minim Martap bauxite project in Cameroon.

  • Limited rail capacity and funding delays have slowed plans to increase production and shipment volumes.

  • The company has withdrawn its previous production forecasts, ore reserve estimate and financial projections linked to its definitive feasibility study.


Australian-listed mineral development and exploration company Canyon Resources is seeking to raise approximately A$70-million through a proposed renounceable entitlement offer to support the development of its Minim Martap bauxite project in Cameroon.

The company plans to offer shares at A$0.034 each, with the proceeds expected to fund remaining development activities and initial working capital needed to achieve its first bauxite shipment.

Canyon said additional funding would also be required to support the mine’s future operations and increase production over time.

Rail Capacity Limits Production Growth

The company faces significant transport constraints as it prepares to begin operations at the project.

Canyon’s existing rail fleet has an estimated capacity of about 35,000 tonnes a month, meaning the company cannot substantially increase mining output beyond what its trains can transport.

To improve monthly volumes, Canyon said it would prioritise commissioning, operational performance, customer arrangements, rail infrastructure and rolling stock.

However, funding delays experienced during 2026 have prevented the company from advancing planned investments in rail infrastructure upgrades and additional trains.

Canyon does not expect to have sufficient funding for major capital expenditure on these improvements during the remainder of 2026. It is also assuming that funding for the previously planned capital programme will not be available in 2027.

Production Expansion Delayed

Canyon said a review of the project’s development schedule and funding requirements showed that the production timetable underpinning its definitive feasibility study (DFS) was no longer achievable.

The company has consequently withdrawn the outcomes of the DFS.

It also warned that increasing rail capacity would take considerable time, with procurement of additional rolling stock expected to take between 14 and 18 months. Shipping delays and limited vessel availability could further complicate the process.

The planned rail expansion is also expected to overlap with the Cameroonian government’s rail upgrade programme, potentially causing further delays to improvements in transport capacity and the mine’s production ramp-up.

Canyon expects to remain heavily reliant on its existing rail fleet for at least the next three years, limiting its ability to increase production and shipment volumes compared with its previous feasibility study projections.

Ore Reserves and Financial Forecasts Withdrawn

Following the withdrawal of its DFS outcomes, Canyon has also withdrawn the previously reported ore reserve estimate for the Minim Martap project.

The company said the reserve estimate was based on the mining, infrastructure and production assumptions contained in the feasibility study and advised investors not to rely on it when making investment decisions.

Canyon has similarly withdrawn production targets and financial forecasts published in its August 31 target statement because they were based on the now-outdated reserve estimate and development assumptions.

However, the company said its previously reported mineral resource estimate remains unchanged, with the prospects for eventual economic extraction still considered valid.

Canyon Plans New Assessment

Canyon intends to update its technical and economic assessment after the project’s initial operating phase provides more reliable information on product quality, operating costs, rail and logistics performance, customer acceptance and funding availability.

The company said its long-term ambition remains to develop the full potential of Minim Martap, but the project’s future development pathway and economics will depend on updated technical, commercial and financial assessments.