KEY POINTS


  • BHP plans to invest up to $17.4 billion to double copper production in South Australia by 2040.

  • The expansion is expected to raise annual copper output to 650,000 tonnes and support its global production target of 2 million tonnes.

  • The project will also increase uranium processing capacity and gold production, with new water and power infrastructure required.


Mining giant BHP has unveiled plans to invest up to $17.4 billion in expanding its copper operations in South Australia, with the aim of doubling regional production by 2040.

The company said on November 23 that it had identified an economically viable pathway to increase annual copper production in the region to 650,000 tonnes. A final investment decision on the proposed expansion is expected in the first half of 2027.

BHP said the expansion would be funded through its existing copper cash flows, with the South Australian operations expected to contribute significantly to its broader growth strategy.

Geraldine Slattery, BHP’s head of Australian operations, said Copper South Australia was a central part of the company’s growth plans and would account for about a third of its projected production increase by 2035.

The expansion is expected to help BHP achieve its global target of producing two million tonnes of copper annually by the middle of the next decade.

Olympic Dam, Carrapateena and Prominent Hill to drive growth

The Copper South Australia portfolio includes the long-established Olympic Dam mine, Carrapateena and Prominent Hill, which BHP acquired through its purchase of OZ Minerals in 2023, as well as the Oak Dam discovery, renamed Ankata.

BHP said the expansion would make the region one of its most important copper growth centres as demand for the metal rises globally.

Copper is increasingly important to electrification, renewable energy, power infrastructure, electric vehicles, digitalisation and artificial intelligence. BHP expects global copper demand to increase by 30% by 2040, reaching more than 45 million tonnes annually.

The company also said that when the value of byproducts such as uranium, gold and silver is included, its Copper South Australia operations would be comparable in output value to Chile’s Escondida, the world’s largest copper mine.

Copper has become increasingly important to BHP’s financial performance, with the division generating more value than iron ore for the first time in the company’s 2026 financial year.

New mining technology expected to lower costs

The South Australian copper operations have faced technical and operational challenges over the years, including complex ore processing, infrastructure limitations and high development costs.

BHP’s expansion strategy will rely on introducing block caving, a bulk-mining method designed to extract large quantities of ore, alongside a two-stage smelting process.

The company expects the technologies to significantly reduce operating costs and improve the economics of its operations.

BHP is targeting an internal rate of return of between 14% and 17% for the expansion, although the development will require substantial investment in mining, processing and supporting infrastructure.

The region’s copper deposits are also known for their technical complexity and high radioactivity, factors that contributed to earlier development plans being shelved over concerns about costs and commodity market conditions.

Uranium and gold production to increase

The expansion will also increase production of other minerals, including uranium and gold.

BHP plans to roughly double the capacity of its uranium processing plant to between 5,000 and 6,000 tonnes annually. The expansion is expected to raise Australia’s contribution to global uranium supply to about 10%.

Gold production from the South Australian operations is also expected to increase by 45% to more than 570,000 troy ounces annually.

The additional production of these metals is expected to strengthen the value of the regional mining complex and provide BHP with further revenue streams alongside copper.

Water and electricity infrastructure remain critical

The proposed expansion faces infrastructure requirements, particularly water and electricity supply, as BHP’s mines are located in the remote and increasingly arid Gawler Craton region of South Australia.

The company currently relies on water from the Great Artesian Basin, a source that has raised concerns among traditional owner communities, including the Arabana people.

To reduce its reliance on artesian water, BHP is considering a 260-megalitre-per-day seawater desalination plant at Cape Hardy on the Spencer Gulf. The water would be transported through pipelines extending hundreds of kilometres to the mining operations.

However, the state and federal governments have yet to commit to the proposed desalination project.

The South Australian government’s Northern Water infrastructure project is expected to reach a final investment decision next year, with its first water supply targeted for 2032.

The expansion will also require upgrades to electricity transmission infrastructure, including a proposed 275-kilovolt transmission line from Davenport, approximately 273 kilometres away.

The availability of reliable water and electricity supplies will remain critical to the project’s development and BHP’s ability to deliver its planned production growth.